Banner
Bar
 
 

We make it our priority to deliver the best solutions to our client's project needs.

We have the ability to complete all phases of an engineering project from planning and design to construction management.

 

Below are example projects.

Moser Plans and Reports

Stormwater Planning Projects

Hydrology and Hydraulic Analysis-Alternatives Evaluation - Implementation Recommendations

 

Upper First Creek Major Drainageway Planning Study

Client: UDFCD, Denver and Aurora

Completion: August 2010

The study updated hydrology for a 40 sq. mi. watershed and evaluated alternatives which included modeling of 20+ proposed master planned detention basins.  The Conceptual Design phase then further defined the recommended improvements. 

Back To Top

Upper First Creek MDP

 

Upper First Creek

Murphy Creek Major Drainageway Planning Study and FHAD

Client: UDFCD and Aurora

Completion: October 2008

The goal of this study was to develop a Master Plan to address flooding, stream stability, and water quality in the Murphy Creak watershed.  The project team sought public input, gather existing information, conduct field investigations, and develop and evaluate alternatives to produce a feasible drainage and flood control plan.  The watershed is rapidly developing and this study will provide the City and developers a guide for future improvements. 

Back To Top

Murphy Creek

Murphy Creek

Channel Restoration Projects

Grade Control-Slope Stabilization-Habitat Improvement-Construction Documents

Rock Creek Channel Restoration - Final Design

Client: Urban Drainage and Flood Control District

Completion: November 2004

Description:
Construction plans were completed for the improvements to the Rock Creek channel through the Carolyn Holmberg preserve in Boulder County.   Due to upstream urban development and the subsequent increase in both base and peak flows, the channel has experienced channel bottom and bank erosion.  To mitigate the problem, design plans and details were prepared for sculpted concrete grade control structures, low-flow channel and slope stabilization measures, improved road culvert crossings, and planting of wetland, riparian and upland vegetation to restore the Rock Creek channel. 

Back To Top

Scultped Concrete Drop Structure

 

Scultped Concrete Drop Structure

Cottonwood Creek Channel Restoration

Client: Southeast Metro Stormwater Authority

Completion: April 2011

Cottonwood Creek is tributary to Cherry Creek and the Cherry Creek Reservoir. The goals achieved in development of the construction plans included channel stabilization, 100-year flood conveyance, prevention of future safety hazards, and safety of public infrastructure. Some proposed structure enhancements to restore Cottonwood Creek were grouted boulder drop structures, stilling basin, and wetland grasses in between buried rock were incorporated in order for the structure to visibly appear more organic and improve water quality functions.

Back To Top

Cottonwood Creek Wetland Drop
                              Structure

 

Cottonwood Creek Wetland Drop Structure


Floodplain Management Projects

HEC-RAS Modeling-Floodplain Delineation- Report Preparation

Hayman Fire Area- FEMA Flood Insurance Study

Client: Douglas County

Completion: July 2004

The flood insurance study included the hydrologic analysis for four tributaries to the South Platte River: Four Mile Creek, Horse Creek, West Creek, and Trout Creek. HEC-HMS was used to model runoff from the watersheds. HEC-RAS was then used to determine the 100-year floodplain characteristics. Digital floodplain data was developed into the appropriate format so that it could be integrated into the County's digital flood insurance rate map.

Back To Top

Flooding in the Hayman Fire Area

 

Flooding in the Hayman Fire Area

Upper First Creek Flood Hazard Area Delineation

Client: UDFCD, Denver and Aurora

Completion: October 2011

The flood hazard area delineation was completed for approximately 2 miles of First Creek and Tributary T Drainageways.  The study goal was to develop updated floodplain and floodway boundaries using HEC-RAS model.  Updated flood maps and flood profiles were developed for the existing condition and with master planned improvements per the IGA between UDFCD, Denver and Aurora.  Numerous flow splits were identified throughout the watershed and analyzed using HEC-RAS.

Back To Top

Flow Splits in First Creek
                              Floodplain

 

Flow Splits in First Creek Floodplain


Drainage Design Projects

Hydraulic Design-Storm Sewers, Channels, Culverts-Construction Documents

Tommy Davis Park/Orchard Road Pedestrian Underpass

Client: UDFCD and Greenwood Village

Completion: November 2009

The primary goals and improvements for Tommy Davis Park and Orchard Road included enlargement of the existing pond, improving the water quality of the pond and trickle channel, and increasing the capacity of the culvert under Orchard Road.  The resulting reconfiguration of trails improved pedestrian circulation and accommodate an underpass under Orchard Road.  Preservation of the flood control storage volume was accomplished through installation of the flow control berm, optimizing the pond grading, and installing the appropriate culvert size under Orchard Road.

Back To Top

Orchard Road Pedestrian Underpass
                              Culvert

 

Orchard Road Pedestrian Underpass Culvert

DIA Terminal Water Quality Pond

Client: Denver International Airport

Completion: August 2011

Moser and Associates Engineering completed the design of a water quality basin to treat the existing and future development conditions of the DIA Terminal area to address the MS-4 permit requirements.  The water quality basin will provide regional water quality for the existing Terminal and take into account the current South Terminal Redevelopment Project and future hotel expansion.  The basin was designed to minimize the amount of maintenance required by DIA.  Construction will begin in October 2011.

Back To Top

Site of
                              Terminal Water Quality Pond

 

Site of Terminal Water Quality Pond

Jefferson County Fairgrounds Detention Improvements

Client: UDFCD and Jefferson County

Completion: July 2008

The Jefferson County Fairgrounds project included construction of an approximately 20 acre-foot off-line detention facility to reduce downstream peak flows and potential flooding.  To divert drainageway runoff into the facility, the design and construction plans included a concrete diversion structure with  a concrete wall to control the diversion weir elevation, concrete box culvert,  and pipe construction.  The project also included an equestrian trail modification to existing drainage structures, installation of a grouted sloping boulder drop structure, and relocation of a sanitary sewer pipe line.

Back To Top

Offline
                              Detention Basin Diversion Structure

 

Offline Detention Basin Diversion Structure

Little Dry Creek Culvert Replacement at Arapahoe Road

Client: UDFCD and SEMSWA

Completion: November 2010

Prior to construction the Arapahoe Road culverts were an 84” corrugated metal pipe (CMP) and a 36” CMP. The capacities of the existing pipes were not adequate to fully convey the 100-year storm event runoff in Little Dry Creek and consequently, Arapahoe Road was overtopped frequently. The improvements installed two concrete box culverts with sizes of 12’x10’ and 12’x8’. The box culverts pass the 100-year storm event without overtopping Arapahoe Road.  The 12’x8’ box was installed 2 feet higher than the 12’x10’ to accommodate a pedestrian crossing and also provide connection to the existing sidewalk along both sides of the Arapahoe Road.  

Back To Top

Arapahoe Road Culvert and Underpass

 

Arapahoe Road Culvert and Pedestrian Underpass


Parks Design Projects

Engineering Services - Infrastructure Design - Park Improvements

Wynetka Ponds Park Improvements

Client: South Suburban Parks & Recreation 

Completion: May 2007

Moser & Associates coordinated with the Architerra Group for design of park improvements including a formalized trail system, a new parking lot, dog park water quality feature, improvements to the existing irrigation pond, parshall flume along the creek, and other drainage features throughout the park.

Back To Top

Wynetka Ponds Park

 

Wynetka Ponds Park

Town of Castle Rock - Gemstone Park        

Client: Town of Castle Rock

Completion: March 2006

The park provides various amenities including a synthetic turf athletic field, in-line skating, picnic locations, along with playground areas.  A Phase III Drainage Report was prepared along with construction plans that included grading, drainage, parking lot, irrigation water line requirements, and a stormwater management plan. 

Back To Top

Gemstone Park

 

Gemstone Park


Examples of Other Services

Construction Observation – Castlewood Library

Client: City of Centennial

Completion: 2004

The ground around an existing 54” metal pipe had collapsed, causing large sink holes in the channel.  The invert of the pipe had suffered corrosion and abrasion, damaging the pipe invert.  The water was flowing outside of the pipe in some locations.  The first phase of the project replaced 290 feet of pipe and a segment of the invert of the 54” pipe was lined with concrete as a temporary measure until the next phase of the project could be funded.  The entire project from conceptual design to end of construction was completed in four months.  Construction management services including construction observation and contract administration were provided.

Back To Top

Concrete Lining Damaged Invert of
                              54" diameter Metal Pipe

 

Concrete Lining Damaged Invert of 54" diameter Metal Pipe

CDOT Region 1- Erosion Control Inspections

Client: CDOT - Region 1

Completion: December 2003

CDOT Region 1 construction projects were inspected for implementation of best management practices (BMPs) and compliance with the NPDES Stormwater Permit Regulations.  The installation and effectiveness of both permanent and temporary BMPs were evaluated and when necessary, recommendations were made to install additional erosion control practices and to improve the performance of existing BMPs.

Back To Top

Inspection of Erosion Control
                              Practices

 

Inspection of Erosion Control Practices



720 South Colorado Blvd, Suite 410 S – Denver Colorado 80246 | phone 303.757.3655 | fax - 303.300.1635 | email - moser@moser-eng.com

copyright© and all rights reserved 2006 moser and associates engineering